Saturday, 11 February 2017

MRP and Safety Stock in SAP PP

The SAP ERP system offers two types of safety stocks: absolute safety stock and safety days’ supply. The absolute safety stock enables the system to subtract it from material availability calculations (net requirements calculations). The safety stock must always be available to cover for unforeseen material shortages or unexpected high demand.

For days’ supply/safety time, the system plans the goods receipt in advance by the period specified as safety time. Thus, planned days’ supply of the stock, in fact, corresponds to the number of days specified as safety time. The system shifts backs the date of the receipts by the number of working days and also takes the factory calendar into account.

You make the relevant entries in the MRP 2 view of the material master. The system refers to the planning of a safety days’ supply as safety time. To consider the safety time, you need to set the Safety time ind. to “1” (for independent requirements) or “2” (for all requirements), and then also give the Safety time/act.cov. in days. Further, you can define deviations from the constant safety time using a safety time period profile (STime period profile field).

MAN Production Planning (PP), SAP PP, All SAP Modules

Let’s take a look at how the safety stock availability can be used in net requirements calculations and also the selection method that the system uses for receipts.

1. Safety Stock Availability


To avoid the unnecessary creation of planned orders for a smaller quantity, which can otherwise be covered by the safety stock, you can define the percentage (share) of safety stock that the system can use in such business scenarios. For example, during the MRP run, the system assesses a shortage of 2 PC of a material. You have, however, maintained a safety stock of 40 PC for this material, which the system doesn’t consider in the MRP run. If you define that a 10% safety stock can be used to account for smaller shortages, which for this example means that 4 PC come from safety stock, then the system can cater to this small requirement or shortage of 2 PC from the 4 PC available from safety stock and no longer creates a procurement proposal.

To define the safety stock parameters, use configuration (Transaction SPRO) menu path, Logistics > Production > Material Requirements Planning > Planning > MRP Calculation > Stocks > Define Safety Stock Availability. For this example, the system can consider 10% of the safety stock for Plnt 3000 and MRP group 0010 for net requirements calculation (see below). You eventually assign the MRP group in the MRP 1 view of the material master.

MAN Production Planning (PP), SAP PP, All SAP Modules

2. Master Data Selection


For material that’s produced in-house, you also create a BOM and routing (or master recipe). There might be several alternatives available for a BOM or a routing, so you can control the selection of alternatives. This ensures that the system is able to assign the relevant BOM and routing to the created planned orders, and it enables you to perform functions such as availability checks, and so on.

With the right control in place, the system automatically assigns the correct selection or alternate in the planned orders created from the planning run. This is accessed and managed in the MRP 4 view of the material master (Transaction MM02) as shown below.

MAN Production Planning (PP), SAP PP, All SAP Modules
SAP Online Guides, Tutorials, Materials and Certifications.

Related Posts

3 comments:

  1. Replies
    1. Looking for the best SAP PP Training in Bangalore, then don't delay join IntelliMindz SAP PP Training in Bangalore. Join our SAP PP training to get hands-on training and practice in SAP PP Software. Any Queries call @ 9655877677. IntelliMindz is the best IT Training Institute in Bangalore with placement, offering 200 and more software courses with 100% Placement Assistance.
      SAP PP Course in Bangalore
      SAP PP Course in Chennai
      SAP PP Online Course

      Delete